Forum Discussion

CX_280703's avatar
CX_280703
Icon for Nimbostratus rankNimbostratus
Jun 16, 2017

Move APM Policy flow to a Macro

Hi there,

 

In the VPE I know you can move around policy items and flows but how can you move a flow into a Macro, e.g. I want a big policy flow out of the way and into a macro and just reference the macro. Possible?

 

Thanks

 

1 Reply

  • Hello CX,

     

    I don't think it is possible to move a branch from the principal VPE to a Macro.

     

    You will need to copy elements in your principal VPE to your macro by adding block by block and one by one.

     

    Then you can add the newly created macro to the principal VPE.

     

    Regards